The deadlines

The tier schedule

From Minimum Instrument
5 November 2023 IPCC Tier 1 Guidelines 4.1(ii)(c)(i): at least Tier 1 within one year of the guidelines taking effect
1 July 2026 (third quarter 2026) IPCC Tier 2 Directive of 11 April 2026
1 January 2027 IPCC Tier 3, its equivalent, or high-level measurement-based methods under other frameworks Directive of 11 April 2026

The practical meaning: every quarterly inventory from Q3 2026 onwards must be at least Tier 2, and the plan to reach Tier 3 had to start well before January 2027, because installing meters and building measurement records takes longer than a quarter.

One-off dates

Date What Code
3 February 2023 LDAR inspection schedule begins (onshore) NG-LDAR-006
5 May 2023 GHG management plan and company-wide inspection plan due, six months after the guidelines NG-GHG-004, NG-LDAR-012
11 April 2026 Standardised templates mandatory NG-MRV-003
1 January 2030 Zero routine flaring NG-TGT-032
2030 or 2031 60% fugitive methane reduction; the guidelines give both NG-TGT-033
2060 National net zero NG-TGT-034

The recurring calendar

Frequency What Deadline
Daily Records of gas produced, flared and vented, from meters, kept three years Continuous
Monthly Gas data return Within 21 days of month end
Monthly Audio, visual and olfactory inspections Monthly, weekly or daily depending on how often the site is visited
Quarterly GHG emissions inventory on the Commission's template Each quarter
Annual Compliance report on LDAR Within the first quarter of the following year
Annual Energy intensity reduction of 2.5% Against a 2020 base

How FieldTruth tracks them

The compliance screen evaluates the covered obligations against the asset's own data on the date you look at it. An obligation whose deadline is close enough to act on is shown as at risk with the number of days left, and the monthly return is checked against its 21-day window using the date the report was actually issued. See Compliance and Tier 3 readiness.