Measured, calculated, estimated

Every number in FieldTruth carries a source state: a label saying how that number was obtained. It is the most important single fact about any emissions figure, and it is printed on every report.

The states

State Meaning Example
Measured Read from an instrument on this source A flow meter on the flare header reports 12.4 MMscf for the month
Calculated Derived from measured inputs by a fixed method with nothing assumed Methane vented, calculated from a metered vent volume and a laboratory gas analysis
Estimated Derived using a published average or an assumption Fugitive methane from barrels produced times the IPCC default factor; or a flare's methane using an assumed 98% efficiency
Proxy Taken from a comparable source because this one has no data Using the sister platform's compressor seal losses
Synthetic Demonstration data FieldTruth's reference asset
Unknown No basis was stated A number nobody can account for

States only get worse

A calculation can never make a number more certain than its least certain input. FieldTruth enforces this with one rule: a result takes the worst state of anything that went into it.

  • A measured volume multiplied by a published factor gives an estimated emission. The volume was measured; the emission was inferred.
  • A measured flare volume run through a mass balance with an assumed destruction efficiency gives an estimated result, even though the volume and composition were measured.
  • The same mass balance with a measured efficiency gives a calculated result.

This matters because it is the whole distance between Tier 2 and Tier 3. Anything else would let a single meter make an entire facility look measured.

Where the state comes from

When you register a source in FieldTruth, its measurement state defaults to estimated, never measured. To mark it measured you name the instrument that measures it. Leaving a field blank can never make a number look better than it is; that is the one mistake the product is designed to make impossible.

When a spreadsheet is uploaded, each row inherits its source's state. A row whose basis cannot be established is unknown, which blocks the dataset from being approved until somebody resolves it. Synthetic rows also block approval, so demonstration data can never reach a filing.

On the report

Section 3 of every FieldTruth report, How each tonne was determined, splits the total by state. It is printed whether it flatters the operator or not. A total made mostly of estimates is not wrong, and at Tier 2 that is normal, but it is not a measurement, and the reader is entitled to know the difference before quoting it.